North London Line Re-Signalling WP 2/6/8

Acting as direct installation resource to Atkins Rail for all Signalling work associated with work packages 2, 6 and 8. Rail Tech are providing 8 flexible signalling installation teams (COSS and Look-out contained within the teams itself), all holding traceable installation records and equipped with calibrated installation tools. Total of 24 staff present on-site with a project output of 28,500 hours to date.

Client

Atkins

Project Value

£2.3 million approx

Duration

June 2008 – Completion date November 2010

Activities Undertaken

Installation of 6x Solid State Interlockings for WP2
Installation and termination in 154 Location Cases.
Installation and termination of 163 Signal heads
Alterations to 45 track circuits
All new disconnection boxes for signals, tracks, AWS, Points and TPWS.
5x Signal moves for platform extensions
6x New interlockings for WP6
New signalling panel and REB works
Management of cable train laying in Telecoms/Signalling/Power cables