Margate Cable Renewals / Track Slew

To facilitate the line speed upgrade in the Margate station area it was necessary to the slew the down main line leading into the station itself over a distance of 300 yards. The existing cable route contained 50 year old lead multi-core power cables controlling the station area going South. Rail Tech Group’s involvement in this project consisted of correlating all affected cables, installing new beta ducting into affected locations and relay room, preparing new cables ready for changeover under SMTH, producing change over lists and planning possessions.

Client

Network Rail

Project Value

£48,000

Duration

November 2009 - December 2009

Activities Undertaken

Attending start up and progress meetings
Correlation of locations and relay room
Update of signalling diagrams/records
Possession planning
Preparing cable change over lists
Preparing cables for change over
Changing over circuits into new cabling under SMTH
Removal of redundant cabling
Completion of all necessary paper work for sign off and handback