Lincoln - Re-Signalling

Acting as direct installation resource to Westinghouse for all Signalling and Telecoms functions associated with this project. Rail Tech Group also supplied commissioning resource with successful handover given back during the final commissioning stages in November 2008. Total of 10 staff present on-site with a project output of 14,312 hours.

Client

Westinghouse

Project Value

£412,000

Duration

October 2007 – November 2008

Activities Undertaken

Installation of Solid State Interlocking
Signalling Cable diversion works
Installation of TPWS/LED Signals
CCTV installation at level crossings
Installation of Point machines
DC Track circuit upgrades
AWS Installation
Location case modifications